Extranet Design
|
|
|
Managing
the design, development, implementation,
and operation of even a moderately sized extranet
can be a long, difficult, and frustrating task. In this
article, we present the primary steps to ensure a successful extranet
development effort. Here, at Horsburgh.com, we have used this
approach successfully on our client's extranet development projects.
|
Problem Definition
|
|
The definition and recording of the problem to be solved is one
of the most often overlooked step of any development effort. A
problem needs to be solved, so the tendency is to jump right in
a solve it. For small, negligible cost efforts this is fine. For
Extranet design, ignoring this step will lead to disaster. Write
down and widely publish the answers to the following questions
and all other questions that are appropriate for your specific
effort. Remember to keep the questions targeted to DEFINING the
problem NOT solving it.
Do We Need an Extranet?
This is an obvious question, but should be taken seriously. For
some businesses the answer is an easy yes, but for others, there
may be better solutions. It is wise to seek professional advice
when answering this question. Having an outside professional examine
this question may cost some money up-front, but they are far less
costly early on the development.
What specific Problems will it solve?
Write down the four, five, ten, whatever, number of problems that
having an Extranet will solve. The problems should be clearly
stated, be very specific, and have testable criteria for success.
Make sure you publicize these problems and get user and management
feedback.
What are our available resources (time, money, and personnel)?
Knowing what your actual resources are at the beginning is critical
for defining the development path. If your budget is low, consider
down-scaling the effort. If time is short, consider using off-the-shelf
products extensively. If your personnel resources are thin, consider
outsourcing. Being realistic about your actual resources will
help you prevent overruns and project disappointments. Promising
a global communication when you only have resources for a toy
telephone will always doom a project. Also, don't be afraid to
tell upper management that the resources are too small for solving
the problem. Believe me, they would rather know up front than
get a surprise during deployment.
What criteria will we use to measure success?
This is an often overlooked step in the problem definition. For
every problem stated, you must define a means for determining
the success of the solution. If you can't think of a success criteria,
then the problem is not defined specifically enough. Stay away
from problem statements such as "We must tie all our remote
offices together." Restate the problem in quantifiable terms,
like: "We need 24x7 1Mbps sustained throughput to each regional
office and 80% uptime with 256Kbps sustained throughput to each
local office."
Should I outsource all, some, or none of the development and
operation?
If you have in-house personnel that are under-utilized or have
time to be assigned to the development process, then keeping most
of the development in-house makes sense. If not, then you can
either hire additional staff or outsource some or most of the
development. I recommend that you do not outsource all of the
development. You must have some in-house expertise available or
at least strong upper management support. Otherwise you may end
up with a very nice system that does not solve your problems.
Strategic outsourcing make sense in most Extranet development
projects. The outsourcing contractor can supply the needed expertise
and personnel at the various development phases. And when a particular
phase is finished, you are not left with a staff member looking
for something to do. You will probably find the up-front
costs of an outsourcing firm to be higher than hiring in-house
personnel. But the long-term savings will be far greater with
a professional outsourcing firm than by retaining in-house personnel.
Remember to make sure you feel comfortable with the outsourcer's
style and abilities. You will working with them very closely.
Don't just choose the largest or best-known source. How you and
your outsourcer "mesh" is far more important than their
list of clients.
Am I upgrading an existing system, converting from a legacy
system, or developing from scratch?
Developing a system from scratch, as strange as it sounds, is
by far the easiest. If you are in this situation, count your blessings.
If not, upgrading an existing system or converting from one or
more legacy systems will be your lot. Fortunately, you will have
a long list of "things that don't work right" to begin
with. Make sure that you fully understand what systems will still
be in place after the migration and how they will be integrated
into your extranet. If your budget is low, then consider using
middleware and "web-like" products to layer on top of
the existing system. With a more moderate budget, you can replace
inefficient systems with newer and more powerful ones. Remember
that computer hardware and bandwidth are cheap. It's the software
and operations that are expensive. Powerful hardware and networks
can make even today's bloated software work faster. With a higher
budget, consider replacing inefficient or outdated portions of
the extranet with newer streamlined hardware and software. If
you are not sure what the "latest and greatest" extranet
products are, hire a professional extranet consultant. Their fee
will be well worth it.
Are the local intranets sufficient to integrate into the extranet?
Try to separate the local intranet issues from the overall extranet.
If you find an intranet that is not ready to be integrated, suggest
an intranet enhancement project and integrate them into the extranet
at a later time.
|
Requirements Analysis |
|
|
Performing a requirements analysis is critical to the success
of any project. Without a clear goal in mind, success is dubious.
There are a number of different philosophies about requirements
analysis: top down, bottom up, inside out, etc. The method I have
found to work the best is as follows:
- Clearly state the problem(s) you wish to solve.
- Identify the users of the completed system.
- Formulate a specific budget - time, money, personnel.
- Ask identified users to specifically state what they expect
the system to do.
- Ask management to specifically state their success criteria.
- Separate their requirements from their "desirements."
Only design to requirements. The enhancement phase is where you
address the "desirements."
- Group and "bubble-up" requirements.
- Generate a prioritized requirements table listing the requirement,
where it came from, the success criteria, and priority. Keep this
table high-level. A table with a dozen requirements will be much
easier to manage than one with hundreds.
- Produce a detailed development schedule including hardware,
software, personnel, documentation, and reviews. Include outsourcing
requirements and long lead-time items.
- Get a sign-off of the requirements, resource allocation, and
schedule from top management before you go any further.
Note that items 4 & 5 will be asked throughout the development
cycle since their responses will change when they see prototypes
and when they are being trained. Be sure to update items 6 through
9 each time.
Beware of getting caught in the cycle of
You: What are your requirements?
Them: I don't know, what can you do?
It's always best to ask very specific questions. Don't worry if
their responses change each time you ask the question. It will
happen, so plan for it.
|
Design & Prototyping |
|
|
There are many design methodologies. The ones I've used
most successfully are 1. Rapid Prototyping (for small to medium
projects) and 2. Structured Development (for large or very complex
projects).
Rapid Prototyping
There are five keys to a successful rapid prototyping methodology:
- Assemble a small, very bright team of programmers, hardware
technicians, designers, quality assurance technicians, documentation
and graphic artist specialists, and a single manager.
- Define and involve a small "focus group" consisting
of users (both novice and experienced) and managers (both line
and upper) from each location. These are the people who will provide
the feedback necessary to drive the prototyping cycle. Listen
to them.
- Generate a user's manual and user interface first. You will
be amazed at what you will find out by producing a user's manual
first!
- Use tools specifically designed for rapid prototyping. Stay
away from C, C++, COBOL, etc. Instead use tools such as Visual
Basic, HTML authoring, and similar development environments.
- Remember a prototype is NOT the final application. Prototypes
are meant to be copied into production models. Once the prototypes
are successful, then begin the development processing using development
tools, such as C, C++, Java, etc.
Structured Development
When a project has more than 10 people involved or when multiple
companies are performing the development, a more structure development
management approach is required. Note that rapid prototyping can
be a subset of the structured development approach. This approach
applies a more disciplined approach to the extranet development.
Documentation requirements are larger, quality control is critical,
and the number of reviews increases. While some parts may seem
like overkill at the time, they can save a project from overruns
especially late in the development cycle. For more information
about how the structured development approach works and detailed
technical and management information, you can contact me via e-mail.
(I've written a handbook on the topic :-)
|
Development & Documentation |
|
instagram 5k followers prada boxers prada swim dr kiran patel house inside prada bag prada shoulder bags prada outlet seattle prada milano logo chatgpt? prada panier bag club uniforms גוצי gucci españa prada panier bag prada cabazon gucci shoe bag chatgpt ban manage followers instagram outlet prices catalina island jazz festival spiky red fruit banning chatgpt new block instagram followers instagram followers active prada pet carrier jack spade fulton prada men's briefcase gucci and prada prada pr17 tommy hilfiger outlet stores prada clothing sale 1k instagram followers bondy bait wig making prada bandeau cinnabon merchandise prada carbon black lentes prada blancos prada rossa black prada barcelona prada moccasin tienda de gucci prada bookbag prada spa david cronenberg jason x prada backpack purse prada shoelaces plus followers instagram juanmanuel de prada price prada shoes prada hand bags instareach instagram followers tommy hilfiger outlets instagram followers discord instagram followers co 3000 instagram followers api chatgpt prada dallas amused bouche bing and chatgpt prada mens crossbody athenian academy charter school clearwater meundies boxer prada espadrille wedge zadig et voltaire outlet instagram followers paypal chatgpt 购买 iko nordic colors instagram followers website prada designer shoes prada loafers used custom captain hats prada downtown orange prada purse prada womens blazer mix.marketing mochila prada prada buy prada perfume carbon eddiebauer.com outlet captain's hat custom t shirts erie pa jailbroken chatgpt dr jacob amrani prada paradoxe dupe instagram premium followers prada pet carrier chatgpt' alfonso prada gucci ttt prada loafers monolith pleasant holidays aaa prada kiss aaa san juan capistrano drag me to hell wikipedia yachting hat rosemont hours iron girl seattle aaa brand
|
Once the requirements analysis is well underway, the prototypes
are working, and the focus groups are becoming happy, it's time
to begin the development. Coordinating hardware and software purchases
and upgrades, network and hardware installation, software development,
documentation guides and manuals, reviews, and testing can become
a full-time job. The key to keeping a handle on all of this to
maintain a good written schedule that everyone can view and to have
periodic "all-hands" reviews. Remember that working
with vendors can be a frustrating experience. Hardware incompatibilities,
software bugs, late deliveries, mistaken cabling requirements,
etc. are more the norm than the exception. Outsourcing can help,
but you must be continually involved to ensure success.
|
Test & Review |
|
|
Testing and Reviews take place throughout the development cycle,
including prototyping, development, deployment, operations, and
enhancements. It never ends. It's wise to place a single individual
in charge of testing and reviews. This is not a popular job, but
it is critical for developing a system that works and meets each
of the requirements. Be sure to empower this person (usually a
quality assurance engineer) with the appropriate authority. Also,
provide them with an appropriately sized staff. Testing is time
consuming, tedious work and preparing for reviews and analyzing
results can take much longer than you might think. Fortunately
this person can save you from being surprised at budget review
time and usually catches most problems before they become too
big. If you outsource this task, make sure that you make it clear
to the others on the team what the outsourcer's role is and what level of
authority they have.
|
Deployment & Training |
|
|
OK, the development is complete, quality assurance is satisfied,
the documentation is ready, the regional, national, and global
network connections are in place, and all the "off-the-shelf"
products have arrived. Now it's time to put everything together.
This can be a highly disruptive time. Make sure that you have
full management support and that they understand the nature and
effect of the installation and deployment disruption. Consider
tying together the intranets using a clustered, incremental approach,
testing each connection. Scheduling training sessions concurrently
with the installation can be an effective use of time. Don't skimp
on the training. Make sure you have training in the budget from
the beginning and don't dip into it. The best way to ensure success
is to effectively train the users so that they will actually use
the system and possibly sing its praises. Also remember that training
is ongoing. New employees or employees being moved or promoted
will need to be trained. Each time enhancements are added, new
training sessions must be scheduled.
|
Operation |
|
|
Extranets usually contain many servers. Tasks such as backups,
bug fixes, software updates, hardware maintenance and upgrades,
print and media services, electronic mail account maintenance,
security patches, and other similar tasks must be performed regularly.
Operation and maintenance of such services require an operations
staff. It is not enough to "let the users take care of it."
If you are providing these services in-house then you will need
on-site support from either an outsourcing agency or in-house
staff. The current trend is to outsource most of these services
including the actual servers to an extranet outsourcing firm.
Outsourcing can result in a substantial savings, especially if
the outsourcer stays current with the hardware, software, and
network upgrades. Just make sure that your provider can supply
the services you require and is available when you need them.
Also, be sure to discuss security requirements with them before
you hire them.
|
Enhancement |
|
|
There is always one thing you can count on: "Requirements
Creep." The more successful the system, the faster requirements
creep will occur. As your users become more sophisticated they
will want more and more capabilities. If you can respond quickly
and efficiently, your users will again sing your praises (and
upper management will definitely take notice :-). Make sure that
you have designed in the ability to add features from the very
beginning. Remember to design in scalability and flexibility at
all phases of development.
|
Help Desk |
|
|
You might think that good manuals and good training would be sufficient
to effectively use your extranet. Not so. A knowledgeable, available,
responsive help desk is critical to the overall success of the
project. Users will always find new uses for a well-designed
system and problems will inevitably occur. Without a help desk,
an extranet can become dated and under-utilized. In my experience,
deployment of an excellent help desk (with telephone, fax, online,
and e-mail capabilities) is the single most important function
that ensures the continued success of an extranet.
|
|